Project data
Project | “Überleiter 6” at Klein-Partwitz |
Location | Lusatian Lake District between Berlin and Dresden |
Purpose | This area is becoming increasingly popular for leisure, which has called for an upgrade of the infrastructure. |
Formwork systems |
|
Special features | A particularly interesting part of the “Überleiter 6” canal link is a localised combination of a bridge, lock and fish ladder. A challenging feature of this combination was the construction of the hollow box bridge deck. Although the project management originally assumed that many special formwork elements would be necessary because of the walls and the edge cantilevers, the NOE team managed to reduce the need for these types of individual solutions to minimum. |
Main contractor | Arge Überleiter 6 consisting of BauCom Bautzen GmbH, 02625 Bautzen DIW Bau GmbH, 01917 Kamenz |
"The NOE formwork design was of great help to us on site and played a large role in being able to finish the works ahead of the scheduled programme.”