Formwork systems in perfect combination
Project data
Project | Prinzenpark Düsseldorf |
Location | Oberkassel, Düsseldorf |
Purpose | Construction of a new office complex |
Formwork systems |
|
Special features | As on almost all construction sites, time was short on this office complex. For this reason the wall elements were concreted using NOEtop framed formwork. This has already proven itself on numerous construction sites and is in use in the XXL dimensions 3.31 x 2.65 m and 5.30 x 2.65 m. Since an area of 8.77 m² or 14.05 m² can be formed in one work step, this system saves a lot of time. |
Client | Brune Immobilien, 40472 Düsseldorf |
Main contractor | Rotterdam Bau GmbH, 40764 Langenfeld |
Formwork and concreting | Meister D.O.O, 40467 Düsseldorf |
"As with almost all building sites, the construction programme for this project was very tight. Because concrete requires a certain time to cure and gain strength, we had to make the formwork ready as quickly as possible. NOEdeck is relatively light and can be erected very quickly. Longitudinal beams and formwork panels can be stripped early and used in other places on site. This system is therefore ideal for the task”
Managing Director of Meister D.O.O
Amir Muminovic