Project data

Project
Climbing Centre Munich

Completion
2015

Location
Munich is home to one of the largest climbing and bouldering centres

Formwork systems

  • NOEtop large-area panels 
  • NOEply formwork facing
Special features
Thanks to the system's integrated bracing, it can be used as beam formwork in which the tie bars can be placed anywhere in the bracing. The special feature of NOEply formwork facing is that it detaches from the concrete and can be used multiple times while still giving the same high-quality fair-faced concrete finish. This avoids discoloured areas on the concrete surface.

Client
Trägerverein der Münchener Sektionen für die Kletteranlage München-Thalkirchen e.V. München

Main contractorGrossman-Bau, Rosenheim

Architect

rgp Architekten,Munich


“To reduce the risks involved, we had to place the concrete relatively slowly. Therefore we were pleased to be using NOEtop. With another formwork panel, the whole thing would probably not have worked”
Günther Aufhammer, Foreman for the project

 


“The NOE products performed well on site and were essential to efficient working”
Franz Huber